Implementing SAP Business One: process, duration and your effort
Implementing SAP Business One takes from around one week to about three months, depending on the scope. As an SAP Gold Partner, init consulting AG implements the system – from the requirements analysis to support after go-live.
This page explains the eight phases of a project, what happens in the workshops and during data migration, and which part your team takes on.
What an SAP Business One implementation includes
Implementing SAP Business One covers every step from the initial requirements to day-to-day operation: requirements analysis, workshops on your processes, process definition, configuration, test migration and testing, training, go-live and support afterwards.
How long this takes depends mainly on the number of users, the scope of the data migration and the customisations. In the project examples of init consulting AG, the range is approx. 1 week for a simple configuration, approx. 3–4 weeks for a standard solution and approx. 3 months for a complex implementation.
init consulting AG is an implementation partner, not the vendor: SAP Business One is made by SAP SE. init consulting AG has been an SAP Gold Partner since 2006 and sells the licences as a Value Added Reseller.
- Service
- Implementation of SAP Business One by init consulting AG
- Phases
- Requirements analysis, workshops, process definition, configuration, test migration and testing, training, go-live, support
- Typical duration
- approx. 1 week (simple configuration) to approx. 3 months (complex implementation)
- Data migration
- Master data, stock, open documents and opening balances from the legacy system
- Training
- Key users and end users, at the head office in Kösching or remotely
- Go-live
- init consulting AG accompanies the live start
- After go-live
- Support via ticket, hotline and remote access
- Partner
- init consulting AG, SAP Gold Partner since 2006
The eight phases of an implementation
This is how an implementation project with init consulting AG works. Small projects go through the same steps, just faster.
Requirements analysis and offer
We record your processes, your current system and your goals and tell you openly whether SAP Business One is the right fit. The result is an offer covering licences, implementation effort and dates.
Workshops per department
In workshops on finance, purchasing, sales and logistics – and, depending on the company, warehouse, production or service – your specialists and our consultants define how the processes should work in SAP Business One. Every agreement is recorded, and every open point gets an owner and a deadline.
Process definition
The workshop results go into the process definition. It describes every process step: what happens in the system, which document is created, who carries it out and which posting it triggers. It is the basis for the configuration.
Configuration and developments
We configure SAP Business One according to the process definition and design forms such as quotations, delivery notes and invoices. Anything the standard does not cover – an extension, an interface, a query – gets its own development or interface definition before it is built.
Test migration and testing
The data from the legacy system is first migrated into a test system. Your key users check the migrated data and run through their processes before live operation starts.
Training
Key users learn the system in intensive training, then all users are trained – in basic boot camps and specialist courses, for example on logistics, financial accounting or CRM, at the head office in Kösching or remotely.
Go-live
On the cut-over date, the final data is migrated and SAP Business One takes over day-to-day operation. init consulting AG accompanies the live start.
Support
After go-live, the support team looks after you via the ticket system, hotline and remote access, installs updates and extends the system as your company grows. More under Support.
What comes over from the legacy system
The basis is a data migration analysis that we prepare with you. It records which data comes from which system, whether it is cleansed beforehand and who checks it after the migration.
What is migrated
- Master data: customers, suppliers, items, G/L accounts
- Quantities and costs, i.e. stock
- Open documents
- Opening balances
An export from the legacy system, for example as an Excel table or via SQL, is often enough. For a switch from Microsoft Dynamics NAV there is a separate page on moving from Navision.
Cleansing before migration
Not every record has to come over. The analysis clarifies, for example, how many customers, suppliers and items had no activity in the last year, whether they can be excluded if they have no open items or stock, and whether number formats should change.
If the know-how for extracting or cleansing the data is not available in-house, we plan the support into the project.
Historical documents
Whether closed documents are migrated, and for which period, is something you decide with us in the analysis. The questions are: are the documents needed in day-to-day operation or only for reporting? Can they be kept outside SAP Business One? Can they follow after go-live?
Cut-over date
The timing of the migration depends on your financial year: at year-end, at the end of a period or mid-year. We agree in advance who in your company checks the migrated data.
What your team contributes to the implementation
An implementation only succeeds with the people who know your processes. How much time this takes differs from project to project; we plan it with you in the project plan.
Name key users
One person for each area involved – for example accounting, purchasing, sales and warehouse – who knows the processes and is allowed to make decisions.
Decide in the workshops
The key users describe how work is done today and agree with us how it should run in SAP Business One. They clarify open points by the agreed deadline.
Provide and check data
Provide exports from the legacy system, sort out old records and, after the test migration, check that the migrated data is correct.
Test and attend training
Run through your own processes in the test system and attend the training sessions, so that everyone can work with the new system on the cut-over date.
How long an implementation takes
Three project examples from init consulting AG. They are guide values, not commitments: the duration depends on your processes, the data migration and the customisations.
| Project | Company | Users | Scope | Duration |
|---|---|---|---|---|
| Simple solution | Service company, annual revenue approx. €2 million | 4 | simple configuration without extensive data migration | approx. 1 week |
| Standard solution | Wholesale company, annual turnover approx. €10 million | 8 (finance, purchasing and sales, warehouse, CRM) | adaptation of some standard reports, forms and the user interface | approx. 3–4 weeks |
| Complex implementation | Manufacturing company, annual revenue approx. €20 million | 20 (finance, CRM, warehouse, purchasing, resource planning, HR) | data import, Outlook, production planning and control, CAD, DATEV | approx. 3 months |
What these projects cost and how licences and implementation add up is shown on the page Prices and costs. A first estimate for your company is provided by the project cost calculator.
What we pay attention to in the project
Four rules from the init consulting AG approach that avoid typical delays.
Decisions in writing
Every agreement from the workshops is recorded, and every open point has an owner and a deadline. If an agreement changes the process definition, the definition is updated.
Define first, then develop
Extensions and interfaces are described in their own definition before they are built. That makes clear what will be created before any effort is spent.
Migrate only what is needed
Records without activity and historical documents only come over if they are needed in operation. This keeps the migration lean and the new system clear.
Test before the cut-over date
The test migration reveals errors in the data while the legacy system is still running. At go-live, only the final balances are migrated.
What matters before, during and after the implementation
Costs, switching systems, training and support have their own pages.
- Prices and costs Licence models, cloud or purchase, and the costs of the three project examples. Read more about Prices and costs
- Moving from Navision What to consider when switching from Microsoft Dynamics NAV to SAP Business One. Read more about Moving from Navision
- Learning SAP Business One Training for key users and end users, in Kösching or remotely – page in German. Read more about Learning SAP Business One (in German)
- Support How to reach the support team after go-live. Read more about Support
Questions about implementing SAP Business One
How long does it take to implement SAP Business One?
In the project examples of init consulting AG, a simple configuration without extensive data migration takes approx. 1 week, a standard solution approx. 3–4 weeks and a complex implementation with production and interfaces approx. 3 months. The decisive factors are the number of users, the scope of the data migration and the customisations.
What are the phases of the implementation?
There are eight phases: requirements analysis and offer, workshops per department, process definition, configuration and developments, test migration and testing, training, go-live and support.
Which data is migrated from the legacy system?
Usually master data such as customers, suppliers, items and G/L accounts, plus stock, open documents and opening balances. Exactly which data is migrated and cleansed beforehand is defined in the data migration analysis.
Are old, closed documents migrated as well?
Only if they are needed. Whether and for which period is clarified in the data migration analysis – including whether the documents can be kept outside SAP Business One or follow after go-live.
What do our employees need to contribute to the implementation?
Each area needs a key user who takes part in the workshops, makes decisions, provides and checks data and runs through the processes in the test system. How much time this takes differs from project to project and is set out in the project plan.
How are the users trained?
Key users learn the system in intensive training, then all users are trained. init consulting AG offers basic boot camps and specialist courses, for example on logistics, financial accounting or CRM, at the head office in Kösching or remotely.
What happens at go-live and afterwards?
On the cut-over date, the final data is migrated and init consulting AG accompanies the live start. After that, the support team looks after the system via the ticket system, hotline and remote access and installs updates.
How much does it cost to implement SAP Business One?
That depends on the scope: implementation, data migration, training and maintenance come on top of the licences. Project examples with costs are shown on the page Prices and costs; the project cost calculator gives a first estimate.
Discuss your implementation project
Tell us about your situation: industry, number of users, current system. In the first conversation we clarify whether SAP Business One is the right fit and what an implementation project would look like for you.
Your contact
- Phone
- +49 2191 4378 556
- Mobile
- +49 152 2195 6896
- Info hotline
- +49 8456 2 78 04-0
- Head office
- init consulting AG
Ruppertswies 14
85092 Kösching, Germany
About this page
Reviewed by Hep Tuscher, Member of the Executive Board (COO) of init consulting AG and responsible for its approach to implementation projects.
Published by init consulting AG, SAP Business One Gold Partner since 2006, in business since 1999. init consulting AG is an implementation partner, not the vendor. SAP Business One is made by SAP SE, Walldorf, Germany.
Last updated
26 November 2026
The project examples are guide values. The offer from init consulting AG is binding.
Sources
- init consulting AG: implementation project documents (workshop agreements, process definition, data migration analysis, development and interface definition)
- init consulting AG: service description for training and support, as of September 2026
- init consulting AG: project examples on the page Prices and costs